The LeBlanc’s Building Timeline
Planned
Start |
Actual
Start |
Event
|
Description
|
-----------
|
07/22/12
|
Lot Hold
| |
-----------
|
07/22/12
|
Contract Signed
| |
-----------
|
07/26/12
|
Loan Application
| |
-----------
|
10/10/2012
|
Loan Approval
| |
08/09/12
|
08/09/12
|
Guardian Appt.
| |
08/17/12
|
08/17/12
|
Flooring & Tile Appt.
| |
08/28/12
|
08/28/12
|
Selection Lock-in
| |
08/29/12
|
08/29/12
|
Preparation: Layout/Stake-out
| |
09/06/12
|
09/06/12
|
Pre-construction Mtg.
| |
09/10/12
|
09/10/12
|
Break Ground
(Week 1)
|
The site is excavated by large machines, with special attention to grading the land to promote proper drainage.
|
09/17/12
|
09/17/12
|
Footings Poured (Week 1)
|
The "footer" is the foundation's foundation, a concrete base below the frost line, upon which the foundation sits.
|
9/21/12
|
Foundation walls poured
(Week 2-3)
|
Load-bearing walls of masonry or concrete create one of four types of foundations: full basement, knee-wall, crawl space, or slab. The foundation is inspected.
| |
-----------
|
9/28/2012
|
Waterproofing
| |
-----------
|
10/1/2012
|
Basement slab poured
| |
09/19/12
|
09/19/12
|
Lumber Delivery
| (The lumber was delivered early; Ryan homes is eager!) |
-----------
|
10/1/2012
|
Framing
(Week4-5)
|
The floor, wall, and roof framing forms the "skeleton" of the home, using Ryan's state-of-the-art panelized construction that improves efficiency and precision while minimizing waste and the risk of error. After framing inspection, exterior finishes are applied.
|
-----------
|
10/8/2012
|
Mechanicals
(Week 6-7)
|
The "heart and lungs" of the house are installed: the heating and cooling system, the plumbing lines, and the electrical system.
|
-----------
|
-----------
|
Insulation
(Week 7)
|
Insulation is installed in walls and attic, with an insulating ability, or "R-factor" appropriate to the local climate
|
-----------
|
10/11/2012
|
Guardian Walkthrough
| |
10/23/2012
|
-----------
|
Pre-Drywall Meeting
| |
-----------
|
-----------
|
Drywall install
(Week 7-8)
|
Interior walls and ceilings are finished with drywall (sometimes called "gypsum board"), then sanded, primed, and painted with a first coat.
|
-----------
|
-----------
|
Siding & Shutters
| |
-----------
|
-----------
|
Mortgage rate lock-in
| |
10/31/2012
|
---------
|
Ceramic/Resilient Flooring
(Week 9)
|
Your choice of ceramic tile or vinyl flooring is installed
|
-----------
|
-----------
|
Trim (incl. cabs & doors) (Week 9)
|
A trim carpenter installs doors, cabinets, and molding.
|
-----------
|
-----------
|
Finishing & Paint (first coat)
(Week 10)
|
After pointing up trim and drywall, interior surfaces are painted ("second paint").
|
-----------
|
-----------
|
Granite installed
| |
-----------
|
-----------
|
Tile (showers and floors)
| |
-----------
|
-----------
|
Trades
(Week 11)
|
Electrical and plumbing professionals install plugs, light fixtures, faucets, commodes, and appliances. Systems are checked and started.
|
-----------
|
-----------
|
Carpet/Wood Flooring (Week 12)
|
Carpet and hardwood flooring are installed according to the specifications. The home is then thoroughly cleaned
|
-----------
|
-----------
|
Final Walkthrough
| |
11/29/12
|
-----------
|
Closing
|
You're on the same timeline as we are. We had our Pre-con mtg the same day as you and broke ground the same day. We have had tile installed this week and are scheduled to close on Dec. 6